View Project Totals

Sage ERP Accpac Project and Job Costing 6.0

View Project Totals

To view totals for a project:

  1. Open Project and Job Costing > PJC Transactions > Contract Maintenance.

Click here for help on the fields on the Contract Maintenance form.

  1. Use the Finder or the navigation buttons beside the Contract field to select the contract you want to review, or type the contract code in the Contract field.

  2. Turn on the tree view, if the contract tree is not already visible.

  3. On the contract tree, click the folder for the project you want to review.

  4. Click the Totals tab on the Project Maintenance form that appears in the panel on the right to view totals (extended cost, labour, overhead, total, revenues, and profit) for all the projects in the contract, including estimated, committed, actuals, and recognized amounts, as well as retainage receivable and retainage payable.

Related topics