View Contract Totals

Sage ERP Accpac Project and Job Costing 6.0

View Contract Totals

To view totals for a contract:

  1. Open Project and Job Costing > PJC Transactions > Contract Maintenance.

Click here for help on the fields on the Contract Maintenance form.

  1. Use the Finder or the navigation buttons beside the Contract field to select the contract you want to review, or type the contract code in the Contract field.

  2. Click the Totals tab on the Contract Maintenance form that appears in the panel on the right to view aggregate totals (extended cost, labour, overhead, total, revenues, and profit) for all the projects in the contract, including estimated, committed, actuals, and recognized amounts, as well as retainage receivable and retainage payable.

Additional information

You can also:

Related topics