Past Due Open Orders Logic

Global Delivery Scorecard Application

DSCDWRLD.gifPast Due Open Orders Logic

Depending on the view that the user selects, the comparison will either be As-Of-Date to Schedule Date (NOT Commit Date) or As-Of-Date to Request Date to determine if an Open Order is Past Due

  1. As-Of-Date to Request Date (Current to Request)

    Scorecard tracks from the Current Date to the Customer Requested Date. Expedite dates, credit holds, temporary holds, and 'grace days' are NOT considered in this comparison. Weekends and holidays ARE considered in the calculation.

    NOTE: This will only be calculated for past-dues (opens). This is a Standard Default calculation.

  2. As-Of-Date to Schedule Date (Current to Schedule)

    Scorecard tracks from the Current date to the Schedule Date. Expedite dates, credit holds, temporary holds, and 'grace days' are NOT considered in this comparison. Weekends and holidays ARE considered in the calculation.

NOTE: This will only be calculated for past-dues (opens). This is a Standard Default calculation.