Scheduling full-day activities
To schedule a full-day activity from the Schedule Activity dialog box
Schedule an activity. In the General tab, select the Start Time and End Time of your day. For example, if your normal start time is 8AM, select 8AM. If your normal end time is 5PM, select 5PM.
When you select the end time, the Use Banner check box is selected.
To schedule a full-day activity from a calendar
From the navigation bar, click Calendar.
From the toolbar, click the Daily button.
Select the date from the calendar.
Using your mouse, select the start time and drag to select the duration. For example, if your normal start time is 8AM, select 8AM. If your normal end time is 5PM, drag your pointer to select 5PM.
Schedule the activity. The Use Banner check box is selected.
The activity displays as a banner on the calendar view.